Orion’s CPP 2027
On 9 June 2026 Orion New Zealand Limited (Orion) formally applied to modify its regulated revenue path via a customised price-quality path (CPP).
Orion have applied to the Commission for a CPP. Its application highlights the challenges facing Orion’s network including ageing assets, population growth in Selwyn and Christchurch, increasing electrification and the need to prepare for more frequent severe weather events. Orion’s CPP application can be found at the end of this page, in the ‘Documents’ section.
The Commission will begin assessing this CPP application after deciding whether it is compliant. We will decide the maximum amount Orion will be allowed to recover from its consumers and the minimum quality of service it must deliver.
We will be inviting feedback as part of our consultation process throughout 2026 with a final decision to be made in March 2027. An outline of our process and indicative timeframes can be found below.
Project timeline
|
June 2026 |
CPP application and Independent Verifier Report received. |
|
August 2026 |
Release of the Notice of Acceptance of CPP application and Process and Issues Paper. Submissions due in August/September 2026. |
|
November 2026 |
Release of our draft decision for consultation. Submissions and cross-submissions due in November/December 2026. |
|
March 2027 |
Release of our final decision. |
|
01 April 2027 |
Orion’s CPP comes into effect. |