Upper North Island dynamic reactive support project
On 11 November 2013 we approved Transpower's proposal to expand the geographical area within which it can test its demand response initiatives.
Transpower considered that testing these demand response initiatives nationally would better meet its goals. The outputs that Transpower was required to deliver under the project’s approval needed to be amended so that Transpower could test its demand response initiatives with participants outside the upper North Island area.
download
Decision and Reasons Paper - Amending the outputs for Transpowers demand response programme in the Upper North Island – 8 November 2013
( 180 KB, PDF )
download
Transpower's responses to Commerce Commissions questions on proposed demand response amendment – 18 September 2013
( 65 KB, PDF )
download
Transpower application for outputs for Upper North Island Dynamic Reactive Support Investment Proposal – 14 August 2013
( 377 KB, PDF )
This page was published 2 days ago