Transpower Major Capital Proposal

Transpower uses a major capital proposal to seek regulatory approval for a major capital investment in the national grid or the high-voltage electricity transmission network.

The Capital Expenditure Input Methodology sets out the requirements Transpower follows when preparing major capital proposals and the criteria the Commission uses to review and approve a major capital proposal.

Grid Upgrade Proposals

A grid upgrade proposal (GUP) is a proposal for major capital investment in the national grid that Transpower prepared under the Electricity Governance Rules and submitted to the Commerce Commission or the former Electricity Commission for approval. After 31 January 2012, Transpower submits major capital proposals instead of the grid upgrade proposals.

 

Individual Major Capital Proposals

Potential Capital Proposals under development:   

 Name Estimated Cost ($millions)   Indicative Application Date Indicative Approval Date
         
Upper South Island Grid Upgrade stage 1
$5
  Jun-12 Sep-12 
         
Timaru Substation Development $8 Jul-12 Sept-12
         
Wilton 110 kV bus rationalisation              $10              Oct-12             Jan-13
         
Upper North Island Reactive Support  $60
  Dec-12
 April-13
         
Upper South Island Stage 2             TBA             Apr-13             Jul-13
         
Waitaki Transmission Development
 $20
2013
2013
         
Lower North Island renewables
             $135
              2013
             2013
         
HVDC pole 2 capacity upgrade              $151               2014              2014/15
         
BPE-WIL A reconductoring (WIL-JFD section)              $20               2015              2015
         

Grid upgrade proposals being reviewed by the Commission:

 Name

 Proposed Cost

($millions)

   Application Date  Indicative Approval Date 
         
Otahuhu Substation Land Purchase  $6.783    16-Jun-11 Jun-12
         
Bunnythorpe Haywards A and B lines conductor replacement investment proposal            $130.5            13-Dec-11            May-12
         

Approved grid upgrade proposals:

Name Maximum Approved Cost ($millions)
  Application Date Approval Date
Kaitaia Capacitor Bank Project Overspend  $2.848    29-Mar-2011  21-Jun-11
         
HVDC - increase in interim grid expenditure $8.0    14-Jun-11  25-Aug-11 
         
         
Kawerau generation export enhancement investment proposal           $9.5         23-Dec 11         18 Apr-12
         

Approved Grid Upgrade Plans are available in the online Archive.

Historic Grid Upgrade Plans assessed by the Electricity Commission

Grid upgrade plans assessed by the Electricity Commission prior to 1 November 2010 are held on the Electricity Authority website.

Otahuhu Substation Land Purchase

Read more

Bunnythorpe-Haywards A and B lines conductor replacement investment proposal

Read more

North Island Reactive Support

Read more

Timaru Substation Development

Read more

Upper South Island Grid Upgrade

Read more

Wilton 110 kV bus upgrade

Read more