On 14 June 2011, Transpower New Zealand Limited applied to the Commission concerning the recovery of the HVDC interim grid expenditure. The former Electricity Commission approved the interim grid expenditure of $6.3 million for preparatory work on the HVDC upgrade project. Details on this proposal and subsequent approval in December 2006 are on the Electricity Authority's website.
Decision
On 25 August 2011, the Commission agreed to amend the approved amount to $8 million.
Project timeline
| Type | Description | Indicative date/s |
|---|---|---|
| Timeframes | HVDC - increase in interim grid expenditure | 14/06/2011 - 25/08/2011 |
Disclaimer
These dates are not official and may change. Please see the Terms and Conditions for further limitations.